The following Members have so far paid the STP charges
. A New update information will be available. Please Call on the LWA to clear any dues. If the Property does not appear in this list , then it means that the owner of the plot has not paid - inspite of repeated requests
.
As we know this is a 'Pay and Use '
service - those who dont figure in the list will not be allowed to connectthe sewage line into the STP in future.
*Scroll to the bottom of the page for the Payments info.
Payments made to the experts - Details - 1st Phase of STP on 2nd Main
* Expected Cost of the 1 phase STP - 14,00,000/-
| # |
Date |
Amount |
Details |
| 1 |
23.1.07 |
1,00,000 |
Paradigm Consultancy - 1st Installment |
| 2 |
24.3.07 |
3,20,000 |
Prakruthi Constructions |
| 3 |
15.6.07 |
60,898 |
Prakruthri - Temp soak Pit 2nd Main |
| 4 |
15.6.07 |
3,92,579 |
Prakruthi - 2nd installment 2nd Main STP |
| 5 |
21.08.07 |
2,88,616.00 |
Prakruthi - payment |
| 6 |
16.10.07 |
1,27,432.00 |
Prakruthi payment |
| 7 |
16.10.07 |
13,435.00 |
TDS |
| 8 |
03.11.07 |
17,500 |
Pumping out Sewage Water from STP |
| 9 |
02.11.07 |
9385.00 |
Purchase of Pump |
| 10 |
05.11.07 |
3,600.00 |
Pump fitting charges |
| 11 |
22.12.07 |
1,25,000.00 |
Prakruthi Payment |
| 12 |
19.01.08 |
93,000.00 |
final Settlement |
| |
Total |
15,82,490.00 |
|
Comments (0)